MIND Real Estate / Closed distribution system operator
MIND Park's closed distribution system.
MIND Real Estate, the company that manages MIND Park, is the licensed operator of the closed distribution system. The operating rules govern connection, power quality, system operation, access and metering.
Regulatory documentation
Documents governing the operation of the system.
The documents below relate to the operation of the closed distribution system. Contact the operator for contractual terms, technical requirements and the billing elements currently in force.
- Open PDF (Serbian)↗
AERS / Licence / 15 April 2021
Licence for electricity distribution and operation of the closed distribution system
Licence issued to MIND Real Estate, registration number 0343/21-ПЕ-ДС, with a validity period of 10 years.
- Open PDF (Serbian)↗
AERS / Decision 312-72/2020-L-I
Decision of the Energy Agency of the Republic of Serbia
The decision under which the licence for electricity distribution and operation of the closed distribution system was issued.
- Open PDF (Serbian)↗
Operating rules / 28 February 2022
Operating rules of the MIND Real Estate closed distribution system
The document governs connection, power quality, safe operation, system access, metering and the obligations of users and the operator.
- Open PDF (Serbian)↗
Amendment to the rules
Decision amending part of the closed distribution system operating rules
The decision amending part of the technical rules of the MIND Real Estate closed distribution system.
- Open PDF (Serbian)↗
Access charge / Applicable from 1 October 2025
Decision on the charge for access to the closed distribution system
The document sets out the tariff elements and the date from which they apply. Current billing arrangements and contractual terms should be confirmed directly with the operator.